Traffic Alerts

The River Road construction project starts south of Devon and extends to Bryn Mawr Ave in the north and south lanes of River Road.
Please see tentative schedule below:

  • Week of September 23rd – September 27th (Monday thru Friday) – Placement of Asphalt Leveling Binder and Traffic Signal work
  • Week of September 30th – October 4th (Monday thru Friday) –  Placement of Asphalt Surface Course
  • Week of October 7th – Pavement Striping and Project Completion

Updated September 20, 2019

 
CLOSURES SCHEDULED AT THE BALMORAL AVENUE INTERCHANGE ON THE TRI-STATE TOLLWAY (I-294)

Extended closure needed for bridge and ramp pavement work, delays are expected

Weather permitting, beginning at 11:30 p.m. on Monday, September 23, the right lane on westbound Balmoral Avenue is scheduled to close to traffic through early October. Once these repairs are completed, the left lane on eastbound Balmoral Avenue and the inside left-turn lane on the westbound side are scheduled to close until the end of October.

In addition, beginning at 11:30 p.m. on Monday, September 23, and continuing through the end of October, one left-turn lane on the ramp carrying northbound I-294 traffic to westbound Balmoral Avenue will be closed to prevent drivers from turning into the work zone.
Construction in this area is being coordinated with the Illinois Department of Transportation.

Updated September 20, 2019